Actions from Central Area Panel meeting 13th June 2023

 

Deadline for staff to respond: : {9am on 10th August}

 

All staff please note Date ACTION completed refers to when the requested action is done (or planned to be done if outstanding) not this form is filled in.

 

Ref & Date Outstanding actions raised

Action

 Officer

Response including what is completed & outstanding

Is Action Completed or Outstanding?

Date Action completed

or planned completion date?

 

 

 

 

 

 

CA1

Community Engagement to contact Norman Williams with information on at which meetings changes to the EDB took place, and how these changes were agreed.

Community Engagement

This is covered in the full reply

Complete

20.06.23

CA2

Geof Gage to contact Norman Williams regarding laundry room reviews and changes to laundry room doors.

Geof Gage

The review of the laundries is in progress and residents will be fully involved in the consultation when this begins. 

Complete

24.07.2023

CA3

Justine Harris to check in with cleaner at Essex Place to ensure cupboard is cleared.

Justine Harris

Complete

Complete

20.06.23

CA4

Geof Gage to arrange for Jamie Smith to contact Norman Williams and Pippin Boardman regarding the doors at Essex Place.

Geof Gage/Jamie Smith

Meeting took place on June 20th with attendance of Norman Williams, Emma Selby, unfortunately Mr Boardman was not invited but will be updated. We are now looking at solutions regarding the doors and undertaking a compliance engineering exercise at Essex Place.

Complete

20.06.2023

CA5

Housing Customer Services to be looked at in more detail as an agenda item at a future meeting.

Justine Harris

To come back to a future area panel as part of the implementation of the new Housing Regulations.  Target Dec 23

Outstanding

 

CA6

Geof Gage to attend the next core group meeting with the contractor providing windows at Craven Vale to raise concerns raised by Rosemary Johnson regarding contractors’ behaviour and report this back to the next area panel meeting.

Geof Gage

Met with project managers and contractors and this has been addressed.

Complete

02.07.2023